Exercise
Task |
Elapsed Days of Work |
Days of Work Remaining |
A |
2 |
0 |
B |
8 |
0 |
C |
4 |
0 |
D |
10 |
4 |
E |
0 |
8 |
F |
0 |
6 |
G |
0 |
3 |
H |
0 |
6 |
Update the MSProject plan to reflect the progress and submit your file along with answers to the following questions:
-
- What is the planned cost of completing the project?
-
- What is the schedule variance as of July 1?
-
- What is the CPI as of July 1?
” style=”display: block; overflow-wrap: break-word; overflow: auto hidden;”>
Complete this exercise in MSProject. You can use your solution to the resources exercise (with the HR Manager available at 100%) as the basis for this exercise.
Your project began on June 1 and it is now July 1. The progress and remaining time on each task is as follows:
Task |
Elapsed Days of Work |
Days of Work Remaining |
A |
2 |
0 |
B |
8 |
0 |
C |
4 |
0 |
D |
10 |
4 |
E |
0 |
8 |
F |
0 |
6 |
G |
0 |
3 |
H |
0 |
6 |
Update the MSProject plan to reflect the progress and submit your file along with answers to the following questions:
-
- What is the planned cost of completing the project?
-
- What is the schedule variance as of July 1?
- What is the CPI as of July 1?