Exercise

 

Task

Elapsed Days of Work

Days of Work Remaining

A

2

0

B

8

0

C

4

0

D

10

4

E

0

8

F

0

6

G

0

3

H

0

6

 

Update the MSProject plan to reflect the progress and submit your file along with answers to the following questions:

 

    1. What is the planned cost of completing the project?

 

    1. What is the schedule variance as of July 1?

 

    1. What is the CPI as of July 1?

” style=”display: block; overflow-wrap: break-word; overflow: auto hidden;”>

Complete this exercise in MSProject. You can use your solution to the resources exercise (with the HR Manager available at 100%) as the basis for this exercise.

Your project began on June 1 and it is now July 1. The progress and remaining time on each task is as follows:

Task

Elapsed Days of Work

Days of Work Remaining

A

2

0

B

8

0

C

4

0

D

10

4

E

0

8

F

0

6

G

0

3

H

0

6

Update the MSProject plan to reflect the progress and submit your file along with answers to the following questions:

    1. What is the planned cost of completing the project?
    1. What is the schedule variance as of July 1?
  1. What is the CPI as of July 1?